Overview
Select the topics below to learn about the I-94 North-South Freeway Project. Use the "Help" link located to the left for detailed information about the tools on this Web site. Some items require Adobe Reader or Windows Media Player.
Project history
- Jump to:
- FEIS/ROD
- Project need
- Public outreach
The I-94 North-South corridor spans about 35 miles and is comprised of:
- Six primary traffic lanes (three in each direction) for most of its route.
- Four northbound lanes that split into east and west directions at the Mitchell Interchange, north of the Airport Spur (WIS 119).
- Ramp and auxiliary lanes at selected interchanges.
- The Airport Spur (WIS 119), which is a four-lane freeway facility.
- Seventeen service interchanges outside of the Mitchell Interchange on I-94, not including the Airport Spur.
The Southeastern Wisconsin Regional Planning Commission (SEWRPC) studied southeast Wisconsin's freeway system from 2000 to 2003. The study recommended full reconstruction of the corridor between 2009 and 2016.
The study recommended additional lanes on I-94, and based on WisDOT's careful analysis of the costs and benefits, as well as the public's input on other design alternatives, the selected alternative is to reconstruct the corridor to an eight-lane freeway with design and safety improvements.
On May 30, 2008, the Federal Highway Administration (FHWA) issued its Record of Decision, which announced the agency's final decision and support to reconstruct the I-94 North-South Corridor to an eight-lane freeway with design and safety improvements. FHWA oversaw the Wisconsin Department of Transportation's (WisDOT) process in considering various alternatives for the I-94 North-South Corridor project and their impacts.
FHWA's decision completes the study phase of the project, which began in January 2006. At that time, the purpose and need for reconstruction of the corridor were determined, as well as the environmental impacts such reconstruction would have on the surrounding area.
Since then, the project has advanced through multiple steps including community workshops, data collection, public information meetings, over 500 stakeholder meetings and community presentations, numerous freeway reconfiguration alternatives and the preparation, review, and finalization of the Environmental Impact Statement (EIS).
Final environmental impact statement (FEIS)
The Wisconsin Department of Transportation (WisDOT) has completed the FEIS on the I-94 North-South corridor.
WisDOT and the Federal Highway Administration (FHWA) prepared an Environmental Impact Statement (EIS) to comply with the National Environmental Policy Act. The EIS explains why WisDOT and FHWA propose to reconstruct I-94, the alternatives considered, and their impacts.
The Draft EIS (DEIS) official comment period began November 16, 2007 and was completed on January 25, 2008.
The following documents are in Adobe PDF format. (Note: some files are large and may take longer to download depending on individual connection speeds. Users may need to zoom in to see details.)
FEIS document
297 pages (3.1 MB)
- Impact summary table
- Contents
- Abbreviations and acronyms
- Purpose of and need for the proposed action
- Alternatives/preferred alternative
- Affected environment
- Environmental consequences
- Final section 4(f) and section 6(f) evaluation
- Public involvement and agency coordination during draft EIS preparation
- Comments and coordination following draft EIS availability and public hearing
Appendixes
- Traffic noise impact summary (345 KB)
- Mobile source air toxics (273 KB)
- Agency correspondence during draft EIS preparation (2.1 MB)
- Agency correspondence on the draft EIS and preferred alternative (2.6 MB)
- Agricultural impact statement: Kenosha and Racine counties (336 KB)
Section 1 exhibits
- 1.1 Study area map
- 1.2 SEWRPC recommended regional freeway reconstruction plan (2003)
- 1.3 Kenosha-Racine-Milwaukee corridor transit and rail alternatives
- 1.4 Levels of service examples
- 1.5 Existing and future traffic volumes and level of service (474 KB)
- 1.6 Existing and future (2035) a.m. peak level of service, Milwaukee County
- 1.7 Existing and future (2035) p.m. peak level of service, Milwaukee County
- 1.8 Crash rates, Racine and Kenosha County
- 1.9 Crash rates, Milwaukee County (433 KB)
- 1.10 Service interchange ramp crashes (ramps with more than 20 crashes) 2000-2004, Milwaukee County
- 1.11 Basic pavement components
- 1.12 Pavement year (360 KB)
- 1.13 Pavement life
- 1.14 Existing substandard roadway elements, Milwaukee County (328 KB)
Section 2 exhibits
- 2.1 Spot improvements (451 KB)
- 2.2 and 2.3 Safety and design improvements - part 1 of 2 (1.8 MB)
- 2.2 and 2.3 Safety and design improvements - part 2 of 2 (1.8 MB)
- 2.2a Full access alternative (1.2 MB)
- 2.4 Concept for Airport Spur-boulevard and landscaping
- 2.5 Airport Spur alternatives (362 KB)
- 2.6 27th Street/I-894/I-43 interchange (250 KB)
- 2.7 Layton Avenue interchange alternatives (350 KB)
- 2.8 College Avenue interchange alternatives (351 KB)
- 2.9 Rawson Road interchange alternatives
- 2.10 Drexel Avenue interchange alternatives
- 2.11 Ryan Road interchange alternatives
- 2.12 27th Street/I-94 interchange alternatives
- 2.13 I-94 reconstruction typical section comparison
Section 3 exhibits
- 3.1 Kenosha County existing land use (387 KB)
- 3.2 Racine County existing land use (422 KB)
- 3.3 Milwaukee County existing land use (378 KB)
- 3.4 Milwaukee County transit system transit routes (443 KB)
- 3.5 Public services and places of worship near study area freeway system (656 KB)
- 3.6 Total population along I-94 corridor (270 KB)
- 3.7 Minority population along I-94 corridor (252 KB)
- 3.8 Minority population along I-94 corridor within Milwaukee County
- 3.9 Milwaukee neighborhoods minority population along I-94 corridor (426 KB)
- 3.10 Families in poverty along I-94 (256 KB)
- 3.11 Families in poverty along the I-94 corridor within Milwaukee County
- 3.12 Watersheds and water crossings along the I-94 corridor
- 3.13 Recreational resources/public use lands along the I-94 corridor
- 3.14 Recreational resources/public use lands along I-94 corridor within the city of Milwaukee
Section 4 exhibits
- 4.1 Kenosha and Racine County indirect effects summary
- 4.2 Milwaukee County indirect effects summary
- 4.3 Future traffic volumes and level of service (476 KB)
- 4.4 Safety and design improvements alternative
- 4.5 Safety and design improvements with added capacity alternative
- 4.6 Six lane and eight lane congestion comparison
- 4.7 AD 1006 form
- 4.7a FAA Requirements for Proximity of Detention Basins to Airports
- 4.7b and 4.7c Floodplain Locations (6 lanes) and (8 lanes) part 1 of 3 (1.6 MB)
- 4.7b and 4.7c Floodplain Locations (6 lanes) and (8 lanes) part 2 of 3 (1.5 MB)
- 4.7b and 4.7c Floodplain Locations (6 lanes) and (8 lanes) part 3 of 3 (1.3 MB)
- 4.8 Wetland impact
- 4.9 Diversion volumes for I-94 construction worst case scenario
Section 5 exhibits
Record of decision
The Record of Decision (ROD) was signed on May 30, 2008. The ROD is a document from the Federal Highway Administration that announced the agency’s final decision and support to reconstruct the I-94 North-South Corridor to an eight-lane freeway with design and safety improvements.
- View the ROD and Appendix A (5.1 MB)
- View the ROD (1.3 MB)
- View the ROD, Appendix A - part 1 of 3 (2.7 MB)
- View the ROD, Appendix A - part 2 of 3 (2.7 MB)
- View the ROD, Appendix A - part 3 of 3 (2.7 MB)
Project need
The I-94 North-South corridor was first built in the late 1950s and early 1960s. Today, safety issues, pavement and design deficiencies, and traffic congestion require full reconstruction and redesign.
Much of the corridor has been resurfaced three times. Additional resurfacings are not cost effective and will not address long-term pavement needs.
Increased traffic
WisDOT's 2002 traffic counts in the corridor range from a low of 74,400 daily vehicles in Kenosha County to over 143,000 daily vehicles near Grange Avenue in Milwaukee County. The 1.5-mile WIS 119 airport spur carries about 26,800 vehicles daily as well. Traffic counts have grown steadily in the past years, with Kenosha County seeing the highest growth.
About 1.3 million people, 28,500 businesses and 595,000 jobs are in these three counties combined. About one in six residents, businesses or jobs are in close proximity to the corridor.
Crashes
From 2000 to 2003, an average of 2.2 crashes occurred in the corridor each day.
| County | Injury Crashes | Fatal Crashes | Total Crashes |
|---|---|---|---|
| Kenosha | 267 | 5 | 750 |
| Racine | 249 | 2 | 770 |
| Milwaukee | 468 | 7 | 1,569 |
Outdated design
Example of a scissor ramp
The Mitchell Interchange handles over 195,000 vehicles per day and includes a mixture of left and right exits. Quick merging and weaving are necessary at the 27th Street and airport exits.
Scissor ramps are also located along the corridor and involve vehicles leaving the freeway onto a frontage road. Vehicles already on the frontage road need to stop and wait for a clearing in vehicles exiting the freeway in order to continue.
Public outreach
Informational videos
- Frank Busalacchi, WisDOT Secretary
Playing time: 3:32 - Jaime Maliszewski, Airport Gateway Association
- Ted Grintjes, City of Franklin
Playing time: 0:52 - Alderman Terry Witkowski
Playing time: 0:25 - Tom Taylor, Mayor of Franklin
Playing time: 0:30 - Yvonne Makowski, citizen of Milwaukee
Playing time: 0:22 - Representative Robert Turner
Playing time: 0:38 - Representative Corey Mason
Playing time: 0:25
Environmental justice (EJ)
WisDOT sought out innovative ways to involve minority and low-income populations to ensure that the construction of the corridor does not create disproportionately high and adverse environmental and health impacts to these communities.
The following documents are in Adobe PDF format. (Note: Some files are large and may take longer to download depending on individual connection speeds. Users may need to zoom in to see details.)
- Environmental Justice analysis, part 1 of 4 (1.5 MB)
- Environmental Justice analysis, part 2 of 4 (2.2 MB)
- Environmental Justice analysis, part 3 of 4 (1.9 MB)
- Environmental Justice analysis, part 4 of 4 (2.2 MB)
Newsletters
- November 2007 (1.3 MB)
- November 2006 (741 KB)
- May 2006 (654 KB)
- January 2006 (361 KB)
Community workshops
A series of four brainstorming workshops were held to gather the public's input for possible improvements. A total of 540 people attended a series of four community workshops on the I-94 North-South corridor study earlier this year. The workshops allowed the public to interact with the study team and share ideas and concerns about the freeway corridor, as well as explore possible solutions. Citizens were encouraged to ask questions, mark their thoughts on freeway maps, exchange information, offer suggestions and present known problems relating to the corridor. From these workshops, WisDOT assembled the ideas and comments into concepts to be presented at the upcoming public information meetings.
Public information meetings (PIM) and hearings
WisDOT held a series of three public information meetings in Milwaukee, Racine and Kenosha counties to present concepts and ideas on possible improvements to the I-94 North-South corridor, extending from the Mitchell Interchange area in Milwaukee to the Illinois state line.
Advisory committees
Three advisory committees were formed as another vehicle for input and outreach.
- The Technical Advisory Committee's (TAC) role is to:
- Engage officials and agencies on key aspects of the study.
- Act as liaisons to their communities.
- Attend meetings or send an alternate.
- Support the process.
- The Community Advisory Committee (CAC) is made up of stakeholders along the corridor from Racine, Kenosha and Milwaukee Counties. The purpose is to:
- Provide feedback on concepts being developed for this study.
- Act as a sounding board/focus group for stakeholder interests along the group.
- Act as mechanism for additional community input into the project development process.
- Disadvantaged Business Enterprise (DBE) Committee and Labor Committee's (Labor Advisory Committee (LAC) and Labor Development Committee (LDC)) purpose is to improve coordination, communication and planning for WisDOT programs and projects within the affected community. This group provides guidance in the areas of training, technical assistance and products to expand capacity and quality of life.
- The Community Sensitive Design Advisory Committee's (CSDAC) role is to:
- Engage officials to determine desired community image.
- Act as liaisons to their communities to communicate community vision.
- Attend meetings or send an alternate.
- Support the study process.
Stakeholder group presentations
The I-94 North-South corridor study team met with many constituent groups.